Harmonic Periods

Description

In real-time scheduling, predictability is very important, i.e., we would like to know the whole schedule before we really run the tasks. Rate-monotonic scheduling is very popular in real-time scheduling for periodic tasks, where tasks with shorter periods have higher priority. However, it is still dicult to know the start time and finish time of each task and they might be dierent in each period, especially for tasks with low priority, i.e. long period. The hyperperiod, the least common multiple of all periods,is usually too big to be practical to describe the whole schedule. However, if the task periods are harmonic, i.e. are multiples, it is possible to find the start time and finish time of each task quickly because the schedule becomes more regular.


Figure 1 shows that periodic tasks T1, T2, T3, T4 with execution times 1, 1, 3, 1 and periods 2, 4, 16, 32 respectively are schedulable, each task finishes execution in its period, using the Rate-Monotonic scheduling algorithm since T1, T2, T3, T4 finish execution at time 1, 2, 12, 16 respectively. T3 is preempted by T1 and T2 at time 4 and time 8 and resume at time 7 and time 11.
Input

All the input numbers are positive integers, < 500000, separated by a space or new line. The first line is the number of task sets. Then, the task sets are listed set by set. Each task set is listed by a line of the number of tasks, <= 100, and lines of task execution time and period pairs, execution time < period. The periods are harmonic, not sorted, and are different in a task set.
Output

For each task set, find and print out the finish time of the task with the largest period using rate-monotonic scheduling, if schedulable; otherwise print out -1.
Sample Input

3
4
1 2
1 4
3 16
1 32
3
1 4
4 8
256 1024
3
1 2
3 8
1 4
Sample Output

16
1024
-1

  • 写回答

1条回答

  • threenewbee 2017-10-05 01:28
    关注
    本回答被题主选为最佳回答 , 对您是否有帮助呢?
    评论

报告相同问题?

悬赏问题

  • ¥30 这是哪个作者做的宝宝起名网站
  • ¥60 版本过低apk如何修改可以兼容新的安卓系统
  • ¥25 由IPR导致的DRIVER_POWER_STATE_FAILURE蓝屏
  • ¥50 有数据,怎么建立模型求影响全要素生产率的因素
  • ¥50 有数据,怎么用matlab求全要素生产率
  • ¥15 TI的insta-spin例程
  • ¥15 完成下列问题完成下列问题
  • ¥15 C#算法问题, 不知道怎么处理这个数据的转换
  • ¥15 YoloV5 第三方库的版本对照问题
  • ¥15 请完成下列相关问题!