Schedule Problem

Problem Description
A project can be divided into several parts. Each part should be completed continuously. This means if a part should take 3 days, we should use a continuous 3 days do complete it. There are four types of constrains among these parts which are FAS, FAF, SAF and SAS. A constrain between parts is FAS if the first one should finish after the second one started. FAF is finish after finish. SAF is start after finish, and SAS is start after start. Assume there are enough people involved in the projects, which means we can do any number of parts concurrently. You are to write a program to give a schedule of a given project, which has the shortest time.

Input
The input file consists a sequences of projects.

Each project consists the following lines:

the count number of parts (one line) (0 for end of input)

times should be taken to complete these parts, each time occupies one line

a list of FAS, FAF, SAF or SAS and two part number indicates a constrain of the two parts

a line only contains a '#' indicates the end of a project

Output
Output should be a list of lines, each line includes a part number and the time it should start. Time should be a non-negative integer, and the start time of first part should be 0. If there is no answer for the problem, you should give a non-line output containing "impossible".

A blank line should appear following the output for each project.

Sample Input
3
2
3
4
SAF 2 1
FAF 3 2
#
3
1
1
1
SAF 2 1
SAF 3 2
SAF 1 3
#
0

Sample Output
Case 1:
1 0
2 2
3 1

Case 2:
impossible

  • 写回答

2条回答 默认 最新

  • threenewbee 2017-06-04 17:49
    关注
    本回答被题主选为最佳回答 , 对您是否有帮助呢?
    评论
查看更多回答(1条)

报告相同问题?

悬赏问题

  • ¥20 基于MSP430f5529的MPU6050驱动,求出欧拉角
  • ¥20 Java-Oj-桌布的计算
  • ¥15 powerbuilder中的datawindow数据整合到新的DataWindow
  • ¥20 有人知道这种图怎么画吗?
  • ¥15 pyqt6如何引用qrc文件加载里面的的资源
  • ¥15 安卓JNI项目使用lua上的问题
  • ¥20 RL+GNN解决人员排班问题时梯度消失
  • ¥60 要数控稳压电源测试数据
  • ¥15 能帮我写下这个编程吗
  • ¥15 ikuai客户端l2tp协议链接报终止15信号和无法将p.p.p6转换为我的l2tp线路